Smash and Grab Adjudications Explained
A Practical Guide for Contractors, Subcontractors and Employers
Payment disputes remain one of the most common causes (if not the most common) of construction adjudications in the UK construction industry.
One of the most widely discussed forms of payment dispute is the so-called "Smash and Grab" adjudication.
Although the term is frequently used throughout the industry, there is often confusion regarding what Smash and Grab adjudications are, when they arise, and why they can have significant financial consequences for both paying and receiving parties.
This guide explains the principles behind Smash and Grab adjudications, how they arise, the legal framework that supports them, and the practical steps parties can take to avoid becoming involved in one.
What Is a Smash and Grab Adjudication?
A Smash and Grab adjudication is typically a payment dispute arising from a failure by the payer (i.e. the Employer to a Contractor, or the Contractor to Subcontractor) to serve a valid:
-
Payment Notice; and/or
-
Pay Less Notice
within the timescales required by the contract and the Housing Grants, Construction and Regeneration Act 1996 (as amended).
In simple terms, the dispute focuses on:
Whether the correct notices were issued on time (and in the correct form),
rather than:
Whether the valuation amount itself was actually correct.
As a result, a contractor may become entitled to payment of the full amount applied for, regardless of the payer's views concerning the true value of the works.
Why Is It Called a Smash and Grab Adjudication?
The case of CG Group Ltd v Breyer Group PLC [2013] is widely cited in industry commentary and legal literature as the early case where the colloquial label "smash and grab" first surfaced to describe claims driven by technical notice failures (see paragraph 25(iii) of that judgment).
It would appear that the phrase arose because some parties perceived these claims as allowing payment to be recovered through procedural failures rather than detailed valuation arguments.
However, the reality is that Smash and Grab adjudications - far from being unmerited or similar - are based upon the statutory payment framework established by Parliament, in the Construction Act, as amended in 2011.
The legislation requires parties to operate clear payment procedures and comply with strict notification requirements.
Where those procedures are not followed, significant consequences may arise.
How Does a Smash and Grab Adjudication Arise?
A typical scenario may look something like this:
Step 1
The Contractor submits an Interim Payment Application (typically towards the end of a given month).
Step 2
The Employer (or appointed person, like a Contract Administrator for example) fails to issue a valid Payment Notice at the correct time.
Step 3
Furthermore, and subsequently, no valid Pay Less Notice is served by the Employer either.
Step 4
The relevant final date for payment of the interim payment in question passes, and payment is not made.
Step 5
Following the failure to issue a Pay Less Notice, or the passing of the final date for payment, the Contractor argues that the amount applied for, in its Payment Application, has become "the notified sum" (as per section 111 of the Construction Act), and is overdue and payable as a debt essentially. The Contractor may demand payment of said sum.
Step 6
If the Employer rejects this argument, the Contractor commences adjudication seeking to recover "the notified sum".
In such cases, the primary issue is not valuation but whether the relevant notices were valid and served on time. There is a plethora of case law on such issues, unsurprisingly.
What Is a Notified Sum?
The concept of the "notified sum" is fundamental to understanding Smash and Grab adjudications. The terms comes from section 111 of the Construction Act.
The notified sum is generally the amount identified in:
-
A valid Payment Notice;
-
A valid Pay Less Notice; or
-
In certain circumstances, the Contractor's application for payment (acting as a default payee's notice).
Subject to the terms of the contract and legislation, the payer is generally required to pay the notified sum by the final date for payment.
Failure to do so may expose the payer to adjudication proceedings.
Why Are Payment Notices So Important?
The statutory payment regime is designed to provide certainty and maintain cash flow throughout the construction supply chain.
Payment Notices perform several important functions:
-
Identifying the amount considered due;
-
Explaining the basis of valuation;
-
Providing transparency;
-
Allowing disagreements to be identified quickly.
Where notices are not issued correctly, the statutory regime may produce outcomes that the payer did not anticipate.
For this reason, payment notices should never be viewed as an administrative formality.
What Makes a Valid Payment Notice?
Although every contract should be reviewed individually, a valid Payment Notice will generally:
-
Identify the amount considered due;
-
Explain the basis of calculation;
-
Be served on time;
-
Be served correctly;
-
Clearly communicate its purpose (it should be clear to the recipient what it is and what it is intended to convey).
The validity of notices is frequently disputed during adjudication proceedings, and is the subject of many court cases. Case law should always be considered when considering the validity of such notices.
For further information, see our guide:
What Makes a Valid Pay Less Notice?
A Pay Less Notice allows the payer to notify a reduced amount where they disagree with the valuation / sum that would otherwise be payable.
A valid Pay Less Notice should typically:
-
State the sum considered due;
-
Explain the basis of the revised valuation;
-
Be issued within the contractual timescales;
-
Comply with contractual service requirements.
Late or defective Pay Less Notices regularly form the basis of Smash and Grab adjudications (as an alternative to arguments relating to Payment Notices, or concurrent with such arguments).
Can a Payer Challenge the Valuation / Amount Due?
This has been one of the most heavily debated issues in construction payment law.
Generally speaking, a payer will be required to pay a genuine notified sum first and then pursue a separate valuation (or "true value") dispute afterwards.
This is consistent with the principle often summarised as:
"Pay now, argue later."
The precise position will depend upon the circumstances, the contract, and the issues in dispute.
Parties should obtain specialist advice regarding their specific situation.
Common Defences in Smash and Grab Adjudications
Not every "smash and grab" claim succeeds. Often, we find that parties are under the mistaken apprehension that having issued a payment application, or invoice, and having received no payment notice (or pay less notice) in return, they will automatically succeed; but this is often not the case.
Common arguments raised by responding parties may include:
No Crystallised Dispute
The responding party may argue that no dispute existed at the point of referral.
Jurisdiction Challenges
Questions may arise regarding the adjudicator's jurisdiction.
No Valid Application for Payment
The application itself may be challenged.
Valid Notice Was Served
It may be alleged that a compliant Payment Notice or Pay Less Notice was properly issued.
Disputed payment provisions
It may be the case that one party alleged that the contract does not contend adequate payment provisions, in whole or in part. The parties may disagree over such matters which can affect timings, which can be key.
Service Issues
Disputes frequently occur regarding how and when notices were served.
The outcome will depend upon the facts of each case, and there is a large amount of case law in this area which needs to be considered against the facts.
Common Mistakes Made by Paying Parties
Many Smash and Grab adjudications arise from relatively avoidable errors.
Missing Notice Deadlines
This remains one of the most common causes of disputes.
Contractual payment dates and notice deadlines should be monitored carefully.
Incorrect Service
A compliant notice that is served incorrectly may still be vulnerable to challenge.
Assuming an Application Is Invalid
Some payers incorrectly assume that an application for payment can, for whatever reason, simply be ignored. That approach can lead to significant risks.
Poor Contract Administration
Inadequate payment procedures frequently create avoidable disputes.
Leaving Matters Until the Last Minute
Notices prepared at the last moment are often more likely to contain errors.
How Can Parties Avoid Smash and Grab Adjudications?
Simple contract administration procedures can significantly reduce risk.
Practical steps include:
Maintain a Payment Calendar
Track all:
-
Due dates;
-
Notice dates;
-
Final dates for payment.
Use Standard Templates
Consistent templates reduce the risk of omissions.
Review Service Provisions
Always comply with contractual requirements regarding service.
Issue Notices Promptly
Avoid relying upon last-minute submissions.
Seek Advice Early
Potential issues should be identified before deadlines expire.
What Happens During a Smash and Grab Adjudication?
Although every adjudication is unique, the process will typically involve:
Notice of Adjudication
The dispute formally begins.
Appointment of Adjudicator
An adjudicator is selected either by agreement or through a nominating body.
Referral Notice
The Referring Party presents its case.
Response
The Responding Party submits its defence.
Further Submissions
Replies and Rejoinders may be exchanged.
Decision
The adjudicator reaches a determination.
Many Smash and Grab adjudications proceed relatively quickly because the issues often focus upon payment notices and contractual procedures rather than complex valuation exercises.
For further details on the Adjudication process, read our guide on the Construction Adjudication timeline.
Are Smash and Grab Adjudications Still Relevant?
Yes.
Although the law has continued to develop, and case law has shown that on certain occasions, due to some error, Adjudicator's decisions in relation to smash and grab adjudications have not been enforced - these unenforceable cases tend to relate to the principles which arose in Hutton Construction Ltd v Wilson Properties (London) Ltd [2017] - Payment Notices and Pay Less Notices remain fundamental parts of the construction payment regime.
Consequently, parties who fail to comply with the contractual and statutory requirements may still face substantial risks.
Proper contract administration remains the most effective way to avoid disputes.
Frequently Asked Questions
What is a Smash and Grab adjudication?
A payment adjudication that commonly arises where a valid Payment Notice or Pay Less Notice has not been served within the required timescales.
Does a contractor automatically win if no notice is served?
Not necessarily. Each case will depend upon the contract, the facts, and the issues referred to adjudication.
Can a payer challenge the true value of the works?
Generally, valuation disputes may be pursued separately following payment of the notified sum.
What is a notified sum?
The amount identified through the statutory payment notice procedure and payable under the contract.
Can a Pay Less Notice prevent a Smash and Grab adjudication?
Potentially, provided the notice is valid and served within the required timescales.
How Can Sum ADR Help?
Payment notice disputes frequently progress to adjudication and often involve complex contractual and procedural issues.
Sum ADR regularly advises contractors, subcontractors, employers and developers in relation to:
-
Payment Notices;
-
Pay Less Notices;
-
Smash and Grab Adjudications;
-
Interim Payment Applications;
-
Construction Adjudication;
-
Contract Administration;
-
Construction Payment Disputes.
Whether you are seeking to recover payment or responding to a claim, obtaining advice at an early stage can help protect your position and reduce the risk of costly mistakes.