Extensions of Time Explained: JCT vs NEC Contracts
A Practical Guide to Delay Assessment in Construction Projects
Delay is one of the most common causes of disputes within the construction industry.
Whether the issue arises from late design information, variations, adverse weather, restricted access, or changes to scope, delays can have serious commercial consequences for both employers and contractors.
One of the key questions in any delay dispute is:
"Is the (sub-)contractor entitled to an Extension of Time?"
The answer depends upon the terms of the contract, the facts of the project, and the method by which the delay is assessed. This guide explains the principles of Extensions of Time under JCT and NEC contracts, the importance of delay analysis, and some of the common issues that arise when assessing entitlement.
What Is an Extension of Time?
An Extension of Time ("EOT") is an adjustment to the contractual completion date where the contractor has been delayed by events for which it is not contractually responsible, and consequently has been prevented from achieving completion by the original completion date stated in the contract.
In simple terms, an Extension of Time protects the contractor from liability for delay damages. Without an Extension of Time, a contractor may become liable for:
-
Liquidated damages ("LAD's")
-
Delay damages
-
Prolongation costs
-
Other contractual deductions
The purpose of an Extension of Time (and the reason for having such clauses in a construction contract) is therefore to ensure that the completion date is adjusted, and that time does not become "at large" i.e. the contractor still has an obligation to finish by a certain known date.
Why Are Extensions of Time Important?
Construction projects rarely proceed entirely as planned.
Changes often occur throughout the course of the works, including:
-
Variations
-
Design development
-
Employer instructions
-
Unexpected site conditions
-
Adverse weather
-
Delayed information
-
Third-party interference
When these events impact progress, the parties must determine:
-
Whether the event has actually caused delay;
-
Whether the delay affects the completion date; and
-
Whether the contractor is entitled to additional time.
Failure to properly assess delays can quickly lead to disputes, adjudications, and in some cases litigation.
Extensions of Time Under JCT Contracts
JCT contracts deal with Extensions of Time through the concept of Relevant Events.
Where a Relevant Event has delayed the contractor's progress, the Contract Administrator ("CA", or other appointed person, depending upon the particular form of JCT contract or subcontract) may grant an Extension of Time.
Common Relevant Events include:
-
Variations
-
Instructions issued by the Employer
-
Exceptionally adverse weather conditions
-
Delayed possession of site
-
Delayed information
-
Statutory undertaker delays
-
Force majeure and other specified events
Under the JCT approach, the CA is generally required to assess the impact of the Relevant Event and determine what adjustment should be made to the Completion Date.
This assessment should be undertaken at the time (i.e. prospectively) but it is often undertaken retrospectively, using information available after the delaying events have occurred. The CA is required to review such matters post-completion, and adjust the overall EOT as necessary.
Extensions of Time Under NEC Contracts
NEC contracts adopt a fundamentally different approach.
Rather than using the concept of Relevant Events, NEC contracts administer such matters via the Compensation Events provisions.
A Compensation Event may entitle the Contractor to both:
-
Additional time; and
-
Additional money.
Common Compensation Events include:
-
Changes to the Scope
-
Project Manager instructions
-
Delayed information
-
Access restrictions
-
Certain physical conditions
-
Employer risks
One of the key features of the NEC process is that assessments are intended to be carried out prospectively. Rather than waiting until the project is complete, the parties are encouraged to assess the likely impact of the event at the time it occurs. This reflects NEC's broader objective of proactive project management, as well as dispute avoidance.
Key Differences Between JCT and NEC
Although both forms of contract deal with delay, the mechanisms are significantly different.
JCT Contracts
-
Extensions of Time arise from Relevant Events.
-
Assessments are often retrospective.
-
The CA/EA determines entitlement.
-
Time and money are intended to be considered separately.
NEC Contracts
-
Extensions of Time arise through Compensation Events.
-
Assessments are intended to be prospective.
-
The Project Manager administers the process.
-
Time and cost are assessed together.
Understanding these differences is essential when preparing or evaluating a delay claim.
What Is Critical Path Delay?
Not every delay entitles a contractor to an Extension of Time (/revised completion date).
To establish entitlement, it is generally necessary to demonstrate that the delaying event impacted the "critical path".
The critical path is the sequence of activities which determines the overall completion date of the project.
If an activity is delayed but does not affect the critical path, it may not delay completion and therefore may not justify an Extension of Time.
For this reason, understanding the project programme, and its critical path, is often central to any delay analysis or assessment.
What Is Delay Analysis?
Delay analysis is the process of assessing what specific events have affected progress and completion, and how.
The objective is to determine:
-
What caused the delay;
-
When the delay occurred;
-
How much delay resulted;
-
Whether the delay affected completion; and
-
Which party bears responsibility.
Delay analysis is frequently required in:
-
Extension of Time claims;
-
Loss and expense claims;
-
Assessing Compensation Events;
-
Adjudications;
-
Arbitrations;
-
Litigation.
Common Methods of Delay Analysis
Several recognised approaches are used within the industry.
The most appropriate method will depend upon the available records, the circumstances of the project, and the purpose of the analysis.
Impacted As-Planned Analysis
This method assesses the anticipated effect of delaying events on the original programme.
Potential delay events are inserted into the baseline programme to determine their likely impact upon completion.
This approach is often used where the project remains ongoing, and it is considered to be one of the simplest forms of delay analysis, but it has its limitations as it does not consider actual progress.
Time Impact Analysis
Time Impact Analysis is commonly regarded as one of the most robust methods of delay assessment, particularly when the analysis is being done contemporaneously.
The method involves:
-
Reviewing accepted programme information;
-
Introducing the delaying event into the programme;
-
Assessing the impact upon completion.
The analysis is undertaken using information which would have been available at the relevant point in time. This approach aligns particularly well with the prospective assessment philosophy of NEC contracts.
Windows Analysis
Window Analysis examines the project in a series of periods or "windows". This can be done in the form of either 'time slice' windows, or 'as-planned vs as-built' windows.
Progress is assessed during each period and delaying events are evaluated in the context of actual project performance.
This method is frequently used in more substantial disputes because it can provide a detailed understanding of changing project circumstances over time.
Retrospective longest path analysis (As-Planned vs As-Built) Analysis
This method compares:
-
What was originally planned; and
-
What actually occurred.
Differences between the two on the retrospective as-built critical path are used to assess the causes and effects of delays.
The approach is relatively simple but can be less reliable on complex projects.
Collapsed As-Built Analysis
This retrospective technique works backwards from the completed project and removes delaying events to assess what completion might have been without them.
Whilst useful in certain circumstances, e.g. when there was no original baseline programme, it is generally more controversial than other methods, as the resultant collapsed programme is seen as being largely theoretical.
What Is Concurrent Delay?
Concurrent delay occurs where two or more delaying events occur during the same period.
Typically, one delay may be:
-
The responsibility of the Employer; and
-
The responsibility of the Contractor.
For example:
-
An Employer variation delays progress by two weeks; and
-
A Contractor labour shortage delays progress during the same period.
Determining entitlement in cases of concurrent delay can be complex and often depends upon:
-
The contract wording;
-
The factual circumstances; and
-
The applicable legal principles.
Concurrent delay remains one of the most frequently disputed issues in Extension of Time claims. Generally, where Contractor delay to completion occurs or has an effect concurrently with an Employer delay, the Contractor's concurrent delay should not reduce any EOT due.
What Records Are Needed to Assess Delay?
Successful delay claims are supported by good project records.
Useful records may include:
-
Contract programmes
-
Updated programmes
-
As-built programmes
-
Progress reports
-
Site diaries
-
Meeting minutes
-
Correspondence
-
Instructions
-
Compensation Event records
-
Photographs
-
Labour records
Where records are poor or incomplete, demonstrating entitlement can become significantly more difficult.
Common Mistakes in Delay Claims
Many delay claims fail due to avoidable errors.
Examples include:
Lack of Programme Information
Without a reliable programme, demonstrating critical delay can be difficult. Many (sub-)contractors often don't ensure that a clear programme is agreed and bound into the contract. A well-prepared contract programme is a beneficial tool which should not be overlooked; it should also be regularly updated throughout the project.
Late Notifications
Many contracts contain notice provisions which should be complied with. Failure to comply can often prohibit contractors from otherwise legitimate claims.
Poor Record Keeping
Insufficient evidence often undermines otherwise legitimate claims.
Failure to Demonstrate Critical Delay
Not every delay affects completion.
It is necessary to demonstrate how the event impacted the critical path (this is made easier if you have an agreed contract programme with a clearly shown critical path on it).
Retrospective Reconstruction
Claims based upon assumptions rather than project records often attract criticism and are less persuasive.
When Do Delay Disputes Lead to Adjudication?
Delay disputes regularly form the basis of construction adjudications; this is due to the fact that questions of 'time' and delay are often inextricably linked to the financial consequences of such delay, and who may be liable.
Common examples include:
-
Extension of Time entitlement
-
Compensation Event assessment
-
Delay damages
-
Liquidated damages
-
Loss and expense / prolongation claims
-
Programme disputes
-
Final account disputes
In many cases, the success or failure of a party's position depends upon the quality of (i) the records it has kept and (ii) the delay analysis undertaken.
Frequently Asked Questions
What is an Extension of Time?
An Extension of Time is an adjustment to the contractual completion date where the contractor has been delayed by events for which it is not contractually responsible.
What is the difference between JCT and NEC delay assessment?
JCT contracts generally assess Extensions of Time through Relevant Events, whereas NEC contracts deal with delay through Compensation Events.
Does every delay entitle a contractor to additional time?
No. The contractor must generally demonstrate that (i) the delaying event is an issue for which it is not responsible, and (ii) the delaying event impacted the critical path and affected completion / the planned completion date.
What is critical path delay?
Critical path delay is delay to activities which directly affect the project's completion date.
What is concurrent delay?
Concurrent delay occurs where Employer and Contractor delays overlap during the same period.
Which delay analysis method is best?
There is no universal answer. The appropriate method depends upon the available records, contract requirements, and the specific circumstances of the project.
How Can Sum ADR Help?
Delay disputes are often technically complex and require both contractual and programming expertise.
Sum ADR regularly advises contractors, subcontractors, employers and developers on:
-
Extensions of Time
-
Delay claims
-
Compensation Events
-
Loss and expense
-
Delay analysis
-
Adjudications
-
Construction disputes
Our team combines practical construction experience with specialist knowledge of contracts, claims, delay analysis and dispute resolution to provide clear, commercially focused advice.